Start 8 to 12 weeks before the move
Internet lines and cabling have the longest lead times, and cabling has to go in before the walls and ceilings are finished. A typical order of work looks like this:
| When | What to do |
|---|---|
| 8–12 weeks before | Order the main and backup internet links. Survey the site and plan cabling, the rack and Wi-Fi. |
| 6–8 weeks before | Install cabling, the rack, power points and the UPS. |
| 4–6 weeks before | Order the firewall, switches, access points, phones and meeting-room equipment. |
| 2–4 weeks before | Configure the network, firewall, Wi-Fi and phone system. |
| 1–2 weeks before | Test internet failover, Wi-Fi coverage, phones and printing. |
| Move week | Set up devices and test every desk. |
| After the move | Finish documentation, check monitoring and confirm backups. |
Internet: two links from two providers
Cloud apps, Microsoft 365 and internet phone systems all stop when the internet does. Order a business-grade main link and a second link from a different provider, ideally entering the building by a different route. A firewall with SD-WAN, such as a FortiGate, switches between them automatically. Size the bandwidth for video calls and cloud backup, not just email.
Cabling and the rack
- Run Cat6 cabling to every desk, plus each access point, printer and camera position.
- Add extra points in meeting rooms and at reception.
- Label both ends of every cable and terminate them on a patch panel.
- Put the rack in a ventilated, lockable space, away from water pipes.
- Keep data cables away from power cables to avoid interference.
Switches and network layout
Use managed switches, with Power over Ethernet (PoE) for phones, access points and cameras. Split the network into separate segments (VLANs) for staff, guests, phones and CCTV or other smart devices, so a compromised camera can’t reach your file server. Write down the IP address plan before anything is configured.
Wi-Fi
- Use business-grade, ceiling-mounted access points managed from one place, not consumer routers.
- Plan access point positions from a site survey, with extra capacity in meeting rooms.
- Keep the guest network completely separate from the staff network.
- Use WPA3 security where your devices support it.
Power backup
Put the rack, firewall, switches and access points on a UPS with enough runtime to bridge to a generator, or to shut down cleanly. Check the earthing and add surge protection. Power cuts and voltage fluctuations are among the most common causes of failed network equipment.
Security from day one
- A next-generation firewall at the edge of the network.
- Endpoint protection on every laptop and desktop.
- Multi-factor sign-in for email, VPN and admin accounts.
- Separate admin accounts, not everyday accounts with admin rights.
Phones and meeting rooms
If you are moving to a cloud phone system such as 3CX, set it up before the move so numbers work on day one. Test desk phones, mobile apps and meeting-room video before people arrive.
Laptops and desktops
Set every device up from a standard build, enrol it in device management (Microsoft Intune comes with Microsoft 365 Business Premium), switch on disk encryption, and record it in an asset register.
Backup
Follow the 3-2-1 rule: keep three copies of your data, on two different types of storage, with one copy off site. Make sure at least one copy can’t be changed or deleted by ransomware, and test a restore before you need one.
Who needs to be involved
- Building management or the landlord, for cable routes, risers, where the internet lines can enter, and power for the rack.
- Your interior contractor, so cabling goes in before ceilings and partitions close.
- Internet providers, to survey the building and confirm installation dates.
- Your IT partner, to design the network and coordinate everyone else.
- A person in your team who can make decisions quickly when questions come up.
Costs people forget
- Testing and certifying the cabling after installation.
- The rack, patch panels and cable management.
- UPS batteries, which need replacing every few years.
- Storage for CCTV recordings, and access control at the doors.
- Meeting-room screens, cameras and microphones.
- A temporary internet connection if the permanent line is late.
Documentation and move day
Keep a network diagram, the IP plan, vendor contacts and every password in a secure password vault. On move day, test every desk point, Wi-Fi in every room, printing, phones and remote access. Keep the old site connected until you have checked everything at the new one.
Frequently asked questions
How early should we start planning office IT?
Eight to twelve weeks before the move. Internet lines and structured cabling take the longest, and cabling must go in before ceilings and walls are finished.
Do we really need two internet connections?
If your team relies on cloud apps, Microsoft 365 or an internet phone system, an outage stops work. A second link from a different provider, with automatic failover, keeps you running.
Wi-Fi or wired network points?
Both. Wired points for desks, phones, printers and cameras give the most reliable connections, and Wi-Fi covers laptops, phones and meeting rooms.